Statistics on Installed Generation Capacity and Electricity Production 2002-2006
| Year | Generation Installed Capacity (MW) (A) |
| Energy Produced (GWh) (B)
|
| Effective Load Factor** C
[=B/(A*8760/1000)]
| ||||||
|
| Thermal | Hydro | Total |
| Thermal | Hydro | Total |
| Thermal | Hydro | Total |
| 2002 | 4,280 | 1,900 | 6,180 |
| 13,210.01 | 6,390.49 | 19,600.50 |
| 0.352 | 0.384 | 0.362 |
| 2003 | 4,280 | 1,900 | 6,180 |
| 15,015.46 | 7,752.67 | 22,768.13 |
| 0.400 | 0.466 | 0.421 |
| 2004 | 4,230 | 1,900 | 6,130 |
| 16,122.04 | 8,086.88 | 24,208.92 |
| 0.435 | 0.486 | 0.451 |
| 2005 | 4,230 | 1,900 | 6,130 |
| 14,542.49 | 6,093.25 | 20,635.74 |
| 0.392 | 0.366 | 0.384 |
| 2006 | 5,099.5 | 1,900 | 6,999.5 |
| 16,345.54 | 6,971.12 | 23,316.66 |
| 0.366 | 0.419 | 0.380 |
|
|
|
|
|
|
|
|
|
|
|
|
|
As indicated in Table 1 below, the analysis conducted by the Task Force indicate that the
total peak load on the entire distribution network is currently just over 9,057 MW, while the
current total capability is 5,758 MW, giving a total distribution gap of about 3,000 MW.
Faced with the gaps outlined in this table, the Government's short term targets are:
*
To close circa 30% of the identified gaps by April 2011. This will increase totaldistribution capability from 5,758 MW equivalent to circa 6,900 MW equivalent.
However, it is important to note that despite this increase in capacity, the total
amount of electricity delivered to customers cannot exceed the "true deliverable"
transformation capacity of the transmission network, which (as described in the
previous section) is unlikely to exceed 5,000 MW equivalent by April 2011.
*
To reduce aggregate distribution losses (technical and non-technical) by at least 5%by April 2011;
*
To secure a noticeable increase in the average number of hours of electricitysupplied to consumers by at least 10% by April 2011.
Table 1: Capability gap analysis for all eleven distribution companies (Discos)
|
| ESTABLISHING THE GAP CLOSING THE GAP
|
|
|
|
| ||
| S/N | DISCO | STATES/AREAS COVERED | DISTRIBUTION CAPABILITY (MW)
| PEAK LOAD DEMAND (MW)
| DISTRIBUTION GAP (MW)
| SHORT TERM GAP (MW)
| MEDIUM TERM GAP (MW)
|
| 1 | ABUJA | FCT, Nassarawa, Niger, Kogi | 515 | 835 | 320 | 106 | 214 |
| 2 | BENIN | Edo, Delta, Ondo, Ekiti | 392 | 1000 | 608 | 202 | 406 |
| 3 | EKO | Lagos South | 796 | 1105 | 309 | 103 | 206 |
| 4 | ENUGU | Anambra, Enugu, Abia, Imo, Ebonyi | 612 | 1017 | 405 | 135 | 270 |
| 5 | IBADAN | Oyo, Ogun, Osun, Kwara | 878 | 1193 | 315 | 105 | 210 |
| 6 | IKEJA | Lagos North | 854 | 1335 | 487 | 162 | 325 |
| 7 | JOS | Plateau, Bauchi, Gombe, Benue | 378 | 507 | 129 | 43 | 86 |
| 8 | KADUNA | Kaduna, Kebbi, Sokoto, Zamfara | 344 | 520 | 176 | 59 | 117 |
| 9 | KANO | Kano, Jigawa, Katsina | 365 | 596 | 231 | 77 | 154 |
| 10 | PORT HARCOURT | Cross Rivers, Akwa-Ibom, Rivers, Bayelsa | 486 | 773 | 287 | 96 | 191 |
| 11 | YOLA | Adamawa, Taraba, Bornu, Yobe | 138 | 176 | 38 | 13 | 25 |
|
|
| TOTAL | 5758 | 9057 | 3305 | 1101 | 2204 |
|
|
|
|
|
|
|
|
|
UNQUOTE
Dear All:I don't know where GEJ wants to get all of this 20,000 MW from o! We should ask for itemization.And there you have it.Bolaji Aluko-----NIPP – National Integration Power Projects: Capacity Projections & Expected Completion Dates
S/N
Name
State
Of
Location
Capacity
(MW)
Expected
Completion
Date
(by Quarter and/or Year)
1
Geregu II
Kogi
434
Y-2012/2013
2
Omotosho
Ondo
451
Y-2021/2013
3
Olorunsogo/
Papalanto
Ogun
675
225MW: Q4-2010
225MW: Q1-2011
225MW: Q4-2011
4
Alaoji
Abia
960
1125MW: Q1-2011
112.5MW: Q2-2011
225MW: Q4-2011
510MW: Y-2012/2013
5
Ihovbor/Eyaen
Edo
450
225MW: Q1-2011
225MW: Q2-2011
6
Egbema
Imo
338
Q2-2011
7
Gbarain/Ubie
Bayelsa
225
112.5MW: Q1-2011
112.5MW: Q2-2011
8
Calabar
Cross-River
563
112.5MW: Q1-2011
112.5MW: Q2-2011
338MW: Y-2012/2013
9
Sapele
Delta
450
225MW: Q4-2010
225MW: Q3-2011
10
Omoku
Rivers
225
Q2-2011
TOTAL
4771
Source: Niger Delta Power Holding Company Ltd. (October 2010)
_________________________________________________________________________
NIGERIA POWER SECTOR SUMMARY INFORMATION
S/N
ITEM
INFORMATION
COMMENT
1
Number of PHCN Power Stations
11
7,122.6 MW (Megawatts)
Sapele, Delta I-IV, Egbin, Shiroro, Jebba, Kainji, Afam I-V, Ijora, [Geregu, Omotosho, Olorunshogo (Papalanto)]
[PHCN – Power Holding Corporation of Nigeria]
2
Number of Existing IPP Power Stations
3
841.5 MW
AES-Egbin, AGIP-Okpai, Omoku
[IPP – Independent Power Project]
3
Total installed generation capacity
7964.1 MW
7,964.1 MW
4
On-Going NIPP Power Stations
10
Geregu (Kogi), Omotosho (Ondo), Olorunshogo (Papalanto, Ogun), Alaoji (Imo), Ihovbor (Delta), Egbema (Imo), Calabar (Cross River), Sapele (Delta), Gbarain (Bayelsa), Omoku (Rivers)
[NIPP – National Integrated Power Projects]
5
Current generation capability
3019.2MW
6
National per capita generation
0.0508KW
Actual: 0.025KW
7
Current estimated national demand
8,000MW
8
Number of transmission companies
(Transcoes)
1
TCN – Transmission Company of Nigeria
9
Transmission line distance
4889.2KM of 330KV
6319.33KM of 132KV
62.50KM of 66KV
KM – kilometers
KV – kilovolts
10
Transmission substations
(i)21# of 330/132KV
(ii) 99# of 132/33/11KV
(i) Total capacity: 6098MVA
(ii) Total capacity: 810.50MVA
[MVA – MegaVolt-Amperes]
[1 VA times power factor – 1 Watt]
[Power factor typically 0.6 – 0.8]
11
Number of Distribution companies
(Discoes)
11
Abuja, Benin, Eko, Enugu, Ibadan, Ikeja, Jos, Kaduna, Kano, Port Harcourt, Yola
12
Average gas demand of existing thermal stations
1,800mmscfd
SCFD – Standard cubic feet per day;
mmscfd stands for million SCFD
One cubic foot of natural gas produces approximately 1,000 BTUs
13
Gas supply to existing stations
500mmscfd
14
Sector Agencies
NERC, REA, PHCN, ECN
http://www.nercng.org , http://www.reang.org/
http://phcnonline.com/, http://www.phcnikejazone.org/about_us.html
See: http://power.cpcstrans.com/index.php?option=com_frontpage&Itemid=1
20
Governing law
Electric Power Sector Reform (EPSR) Act 2005
http://www.fmp.gov.ng/index.php?option=com_docman&task=doc_download&gid=23&Itemid=115
PHCN – Power Holding Corporation of Nigeria
MW – Megawatts
SCFD – Standard cubic feet per day; mmscfd stands for million SCFD
MVA – MegaVolt-Amperes
IPP – Independent Power Project
NIPP – National Integrated Power Projects
NERC – National Electric Regulatory Company http://www.nercng.org
REA – Rural Electrification Agency of Nigeria http://www.reang.org/
ECN – Energy Commission of Nigeria http://www.energy.gov.ng/
_________________________________________________________________________
Jonathan promises 20,000mw by 2015
Domestic power generation in this country would rise to 20,000 megawatts by 2015 and would meet the needs of manufacturing industries many of which currently generate their own power, President Goodluck Jonathan said in Abuja yesterday.![]()
He spoke while presenting his administration’s blueprint on power, agriculture and Niger Delta to former British Prime Minister Tony Blair and the Chief Executive Officer of JP Morgan Bank of the USA, Mr. Jamie Dimon. He also vowed to implement the action plans to their logical conclusion.
Jonathan told the visitors at the State House, Abuja, that if his administration’s plans for the power sector are fully implemented, Nigeria should be generating enough power for use in homes, offices and commercial enterprises by April next year.
He also briefed them on his administration’s efforts to boost agricultural production in the country through large scale commercial farming as well as measures being taken to sustain peace in the Niger Delta. He said the Federal Government was also tackling challenges in the area of power transmission and that it intended to move as quickly as possible on the construction of a new National Power Transmission Super-Grid to replace the existing grid which can no longer meet the nation’s power transmission needs.
He told Blair and Dimon that Nigeria would welcome support from international finance organizations and global banks such as JP Morgan through long-term financing for the super-grid project which is critical to assuring the sustainability of stable power supply in the country.
Blair told Jonathan that there was a huge amount of goodwill in the international community towards supporting his efforts to achieve rapid socio-economic development in Nigeria. The former British Prime Minister said the decision by JP Morgan, one of the world’s largest banks, to upgrade its representative office in Nigeria to a full-scale branch was a vote of confidence in Nigeria and the Jonathan administration.
Also yesterday in Abuja, Jonathan received the Foreign Minister of the Russian Federation Mr. Sergey Lavrov, who is in the country to follow-up on the implementation of bilateral agreements signed during President Dmitry Medvedev’s official visit to Nigeria last year. Jonathan assured Lavrov that his administration will do all it can to facilitate the implementation of the agreements and the expansion of areas of economic cooperation between Nigeria and the Russian Federation.
------
--
You received this message because you are subscribed to the "USA-Africa Dialogue Series" moderated by Toyin Falola, University of Texas at Austin.
For current archives, visit http://groups.google.com/group/USAAfricaDialogue
For previous archives, visit http://www.utexas.edu/conferences/africa/ads/index.html
To post to this group, send an email to USAAfricaDialogue@googlegroups.com
To unsubscribe from this group, send an email to USAAfricaDialogue-
unsubscribe@googlegroups.com



No comments:
Post a Comment